Vitol Power International – Immingham

VPI Sub1 front view of air conditioning installation by Torr Engineering

Humber Bank combined heat & power generator, VPI, commissioned Torr Engineering to replace a failing chiller system providing cooling to a large substation electrical switchroom.

VPI is one of the largest, cleanest & most efficient CHP plants in Europe, capable of generating 1,240 megawatts – about 2.5% of UK peak electricity demand.
VPI also produces 930 tonnes of steam per hour, which is used by nearby oil refineries; Conoco Phillips 66 & Lindsey Oil Refinery to turn crude oil into products such as gasoline.

Vitol Power International (VPI) pictured illuminated at dusk.
Vitol Power International (VPI).

After a twin Lennox ducted chiller system, cooling a large substation electrical switchroom, reached the end of its economically serviceable life, Torr were commissioned to design a system that was efficient, less prone to breakdown, provided 100% redundancy backup and was in budget.

Two options were investigated & presented in detail. The first was to replace the existing Lennox ducted chiller with a similar system; utilising the existing ducting with additional new branches to serve a recent extension to the substation.
This option was finally rejected due to the additional substation floor space that would be taken up by the new air handling units, and because it was significantly more expensive than the second option.

The second and chosen option was to use a network of ceiling cassette split air conditioning systems. The benefits of this option were no impact on floor space, more easily serviceable units, the reduced impact if any one part of the system went down and a saving on the cost of using a similar chiller system previously installed.

16 Mitsubishi Heavy Industries indoor fan coil units delivered and ready for unpacking in the electrical substation at VPI Immingham.
16 indoor fan coil units delivered and ready for unpacking.
1 of 2 small battery rooms that provide an uninterrupted power supply to the VPI substation.

The new system comprised of 14 indoor ceiling cassette air conditioning units to serve the main switchroom, and 2 indoor ducted systems to serve 2 UPS battery rooms, attached to the substation, that provide an uninterrupted power supply to vital equipment in the event of a power cut.

A view of the VPI substation before the installation started.
Prior to the installation starting – a nice clear run for the main bank of services.
Once all the indoor units had been installed, the first bank of pipe work is clamped in place in the electrical substation at VPI Immingham.
Once all the indoor units had been installed, the first bank of pipe work is clamped in place.
The main bank of pipe work & drainage is run the full length of the substation prior to teeing off to each individual indoor unit in the electrical substation at VPI Immingham.
The main bank of pipe work & drainage is run the full length of the substation prior to teeing off to each individual indoor unit.
All the pipe work is turned towards the point of penetration in the electrical substation at VPI Immingham.
All the pipe work is turned towards the point of penetration...
The penetration is cut in the electrical substation at VPI Immingham.
The penetration is cut…
Air conditioning pipe work & services are turned through the penetration to outside the VPI substation.
…And the services are turned through the penetration to outside.
A Big Foot frame system is erected to mount the condensing units on outside the electrical substation at VPI Immingham.
A Big Foot frame system is erected to mount the condensing units on.
The condenser pipe work is completed, a side view of the VPI substation condensers.
The condenser pipe work is completed…
An air conditioning electrical control & change over panel being installed by Torr Engineering at VPI Immingham.
During which time the system cabling is run & the control panel is wired up.

More VPI installation pictures:

Throughout the 10 week project we installed…

1,000 metres of copper pipe

160 metres of metal uni-strut

600 pipe clips

And over a kilometre of wiring!

A before & after view of the high level pipe mechanical services.

A before view of the high level pipe mechanical services.
An after view of the high level pipe mechanical services.

The installation as a whole is split in to 2 separate systems, A & B.
The indoor units for each system are distributed evenly throughout the substation.

A Changeover panel runs system A for 1 week, then switches over to system B for 1 week, with either system being able to satisfy the cooling demands of the substation – providing 100% redundancy backup.

Air conditioning change over control panel in the electrical substation at VPI Immingham.

The changeover panel also has the ability to bring in the standby system, if a high temperature set point is reached, so both systems and all air conditioning units run at the same time.

This provides emergency backup in any period of exceptionally hot weather, although all throughout the 2019 – the hottest summer on record, the standby system was never called in to action. If it ever was, it would provide a total of 192kW of cooling at peak output.

A bespoke stainless steel pipe penetration hood at VPI Immingham. Designed, laser cut and tig welded by local engineering company Mirus Machine Services Ltd of Grimsby.
The finishing touches to the installation were bespoke stainless steel pipe penetration hoods.
These were designed, laser cut and tig welded by local engineering company Mirus Machine Services Ltd of Grimsby.

The completed VPI Substation installation.